Dubai International Airport, T3 (Page 1)
Anno di completazione 2008
Construction of Terminal 3 began in 2004 as next stage of phase 2 of the development, with an estimated cost of around $4.55 billion. Originally planned for completion in 2006, the date was delayed by two years. On 30 May 2008, a topping out ceremony for the terminal was conducted. The terminal became operational on 14 October 2008, with Emirates Airline (EK2926) from Jeddah, Saudi Arabia, being the first flight to arrive at the new terminal, and EK843 to Doha, Qatar being the first departing flight.